Industrial Project and Equipment Supply Agreements – Ways to Achieve Higher-Quality Agreements and Minimise Risks

Light surfaces, LIEKE L-symbol

In October, our experts Helena Kalmanlehto and Markus Pulkkinen organised a webinar on industrial project and equipment supply agreements. Such agreements often contain provisions that may give rise to significant risks and should therefore be addressed in advance to avoid subsequent ambiguities and disputes. The starting point is to focus carefully on the content of the agreement and to strive to draft the contractual clauses in a way that there is as little room for interpretation as possible.

In this blog post, we discuss the most common problem areas in project and equipment supply agreements, as well as ways to avoid these problems.

Defining the subject matter of the procurement and scope of supply

A key aspect of drafting an equipment supply agreement is the precise definition of the subject matter of the procurement. An unclear definition of the equipment to be supplied or the scope of supply is one of the most common causes of disputes. Simply naming the equipment or providing a general technical description is not sufficient if the allocation of responsibilities for design, installation, training or obtaining permits remain undefined. The agreement should clearly state what is to be supplied, with what specifications, and who is responsible for each component or stage of the work.

It is also important to define the allocation of responsibilities where several different suppliers are involved in a project. In such cases, the boundaries of responsibility between the deliveries of each supplier should be carefully defined and set out in the agreement.

Selection of general terms and conditions

General terms and conditions are frequently used in project and equipment supply agreements. These general terms and conditions are often drawn up by an organisation or other institution, but they may also be the other contracting party’s own general terms and conditions.

Particular attention should be paid to the selection of general terms and conditions. It is often safest to choose the terms typically used in similar supply agreements within the relevant market. In any case, the general terms and conditions must be studied carefully.

When selecting general terms and conditions, it is particularly important to consider whether the terms are suitable for the supply in question and its particular characteristics. If, for example, the main focus of the agreement is on the supply of equipment, it is generally not advisable to use terms and conditions primarily intended for construction projects, even if the supply also includes installation. Where necessary, bespoke contract-specific terms and conditions must be drawn up and their precedence over the general terms and conditions in the application of the agreement must be ensured.

Liability for defects and delays, and limitations of liability

When agreeing on liability for defects and delays, it is essential to clearly define their scope and the associated consequences. Contractual penalties and damages for delay are commonly used legal sanctions in equipment supply agreements. These should be proportionate to the potential harm and damage that breaches may cause to the other party, bearing in mind the ‘carrot and stick’ approach. It may also be sensible, for example, to link various bonuses to the achievement of specific interim targets.

In addition to contractual penalties and damages for delay, it is advisable to include clear terms in the agreement regarding, for example, compensation for damages, termination or set-off.

On top of the liability for defects and delays, attention should be paid to limitations of liability. Limitation of liability clauses usually cap liability for damages at a specified amount and/or exclude liability for indirect loss.

Warranty terms and performance guarantees

It is important to distinguish between a so-called ‘standard’ warranty and a performance guarantee, and to define them clearly in the agreement. A warranty is a promise that the equipment to be procured will meet the agreed requirements, as well as the contracting party’s obligation to rectify any defects for which they are responsible that become apparent within a specified period, whereas performance guarantees concern a specific commitment concerning, for example, a device’s production capacity, availability, energy consumption or emissions. In addition to defining the performance guarantee itself, the test conditions or measurement methods used to verify performance must be clearly defined. It is also important to ensure that the agreement specifies the consequences should the equipment fail to perform in accordance with the agreement’s objectives.

Specific issues relating to warranties include various latent defects, design flaws and matters concerning the warranty periods for spare parts, which should be dealt with separately in the agreement. For example, a longer-than-normal warranty period may be specified for latent defects, or it may be agreed that, in the event of a design flaw, the client is entitled to demand repairs to all equipment affected by the design flaw.

Agreements on servicing and maintenance

It is advisable to discuss servicing and maintenance at the time of procurement. The client can then benefit from a stronger negotiating position and predictable costs, whilst the supplier, in turn, benefits from a long-term client relationship. However, the problem with a long-term maintenance agreement is that any ambiguities may persist throughout the long contractual relationship, and pricing errors may recur.

Risk management in a maintenance agreement requires, at a minimum, a precise definition of the tasks covered by the agreement and a clear distinction between these and tasks subject to additional charges or, for example, warranty liabilities. It is also essential to define the supplier’s obligations regarding reporting and invoicing.

Preparing for insolvency risks

When drafting agreements, it is also advisable to pay attention to potential insolvency risks relating to the contracting party. To this end, it is important to specify precisely in the agreement, amongst other things, the transfer of ownership of the equipment. The significance of ownership generally becomes apparent in situations where a contracting party goes into bankruptcy, in which case the assets that the debtor held when it filed for bankruptcy or thereafter belong to the bankruptcy estate. The transfer of ownership of the equipment to a company that has been declared bankrupt means that the equipment forms part of the bankruptcy estate, regardless of whether the supplier has received payment for it or not. To guard against this situation, it is advisable to include a retention of title clause in the agreement, which protects the party supplying the equipment before payment is received. However, one cannot rely on the protection afforded by a retention of title clause in all circumstances. For example, if the equipment is attached to the client’s premises, the clause becomes ineffective. Consequently, the supplier should ensure that payment for the equipment is actually received before it is installed on the premises.

Security is often the most effective and only way to safeguard a contracting party’s position in the event of the other party’s bankruptcy. In equipment deliveries, security is typically provided by the supplier, but the client may also be required to provide security for payment of the contract price, for example, if the client is known to be in a weak financial position when the agreement is concluded.

There are many different types of security and guarantee arrangements, and the contracting party should ascertain what type of instrument is involved and how it operates legally in different situations. The beneficiary of the security should also verify that the security provided is indeed effective and sufficient.

Dispute resolution clauses

Choosing the right method of dispute resolution is important. Disputes may only be referred to arbitration for resolution if the parties have agreed to this. Arbitration is particularly well-suited for large international projects, as it allows for a flexible process in which experts in the relevant field act as arbitrators, and it significantly facilitates the enforcement stage. In smaller domestic transactions, court proceedings may be the preferable choice.

Care should be taken when drafting an arbitration clause to avoid any surprises later on. The arbitration clause should specify, at a minimum, the relevant arbitration institution and the rules of arbitration, the seat of arbitration, the applicable law, the composition of the arbitral tribunal and the language of the proceedings. In large-scale projects, it is advisable to include exactly the same dispute resolution clause in every agreement, so that disputes relating to the same project can, if necessary, be dealt with in the same proceedings.

Caution is advisable with so-called ‘tiered’ dispute resolution clauses: for example, an obligation to negotiate or mediate in good faith before commencing arbitration may, if worded too restrictively, give rise to tedious procedural scrutiny in the event of a dispute. Similar problems can easily arise from clauses where an attempt has been made to direct a dispute to different dispute resolution proceeding based, for example, on the amount in dispute or the nature of the claim. Such clauses should be avoided or, at the very least, it is advisable to have them reviewed by an expert before the agreement is finalised.